Aberdeen Hydrogen Hub

Scotland

Project Factsheet

The Aberdeen Hydrogen Hub is a phased green hydrogen development located in North East Scotland, designed to deliver a scalable production, storage and distribution system to support transport decarbonisation and regional energy transition. Phase 1 includes a 2.5 MWe electrolyser system producing up to 800–1,000 kg of hydrogen per day, sufficient to fuel local bus and vehicle fleets, with the potential for future expansion alongside growing demand. 
Fichtner was initially appointed by Aberdeen City Council to support early-stage development of the programme, delivered in partnership with Opportunity North East and Scottish Enterprise. The role focused on enabling a public–private joint venture, including comprehensive procurement support, development of technical evaluation criteria, assessment of bidder submissions, and interpretation of commercially sensitive parameters influenced by technical performance and lifecycle considerations.
Fichtner subsequently supported multiple follow-on projects and was most recently appointed as Owner’s Engineer for the re-commissioning of two existing electrolysers and development of a new hydrogen refuelling station. The technical scope included detailed review of contractor design documentation, equipment selection, and system integration, alongside active participation in DSEAR compliance assessments and HAZOP studies to evaluate safety and operability. Recommendations were provided to strengthen system design in line with industry standards and regulatory requirements.
Additional responsibilities included construction-phase support, review of tender returns, management of project risks, and administration of contracts. Fichtner also supported variation management, resolution of on-site equipment issues, environmental compliance with SEPA permitting, and verification of factory and site acceptance testing.
Deliverables included technical evaluation frameworks, design and safety reviews, site and commissioning assessments, and cost and programme commentary.

Electrolytic hydrogen production capacity
kg/day hydrogen output
Key Facts

Engineering support for a hydrogen hub

  • Joint venture procurement and bid evaluation
  • Site selection and infrastructure feasibility studies
  • Owner’s Engineer services (design and construction)
  • Design review and technical assurance
  • Safety studies (DSEAR, HAZOP) and compliance review
  • Contract administration and risk management
  • Testing, commissioning, and acceptance support
  • 2.5 MWe electrolytic hydrogen production capacity
  • 800–1,000 kg/day hydrogen output for transport use 
  • Scalable hydrogen hub supporting regional energy transition