Fichtner provided Technical Advisor and Vendor Due Diligence (VDD) services for Gate Burton Energy Park, a proposed 500 MW solar PV and battery energy storage (BESS) development in Lincolnshire, capable of powering over 160,000 homes and avoiding more than 100,000 tonnes of CO₂ annually.
Appointed by Low Carbon at Development Consent Order (DCO) stage, Fichtner supported a strategic equity investment process through delivery of a comprehensive technical review of the evolving project design. Our scope covered site conditions, land arrangements, and PV and BESS system concepts, identifying opportunities to optimise layout, improve performance, and enhance project bankability.
We undertook an independent energy yield assessment (EYA) to evaluate performance sensitivities and inform system optimisation, alongside providing specialist input on BESS design, including operational strategy, safety, insurability, and revenue considerations.
Fichtner also reviewed the grid connection strategy, including the connection offer, curtailment risks, and wider network impacts, and supported development of the grid concept, cable route, and electrical design.
Our work resulted in a Technical Due Diligence (TDD) report, supported by design reviews, optimisation recommendations, and cost-focused commentary.