The Hydrogen for the Decarbonisation of Sheffield Steel (HYDESS) project is a low-carbon hydrogen initiative located at E.ON’s Blackburn Meadows renewable energy park in Sheffield, UK. The project is designed to enable the production and use of green hydrogen within the local steel sector, supporting fuel switching from natural gas and reducing industrial emissions. Studies indicate potential hydrogen production of approximately 200 kg/h, equating to around 1,500 tonnes per year, with scalability aligned to future demand.
Fichtner was engaged by E.ON to deliver feasibility, pre-FEED and full FEED services under the UK Government’s Industrial Hydrogen Accelerator (IHA) Programme. The initial phase established the technical and commercial case for hydrogen integration, including development of electrolyser selection criteria, supplier engagement, and coordination with consortium partners to support funding applications.
The technical scope included assessment of electrolyser technologies, preparation of RFI documentation, and concept design studies to define capacity and site integration. This progressed into FEED, including preparation of a Basis of Design, Thermoflex mass and energy balances, and development of detailed engineering documentation such as PFDs, P&IDs, equipment schedules, plant layout, electrical load lists, and control architecture. Fichtner also reviewed environmental permitting implications, assessed water and wastewater requirements, and developed a Project Execution Plan.
In addition, Fichtner prepared CAPEX and OPEX estimates to AACE Class 3 standard, supported civil cost development, and continues to provide commercial modelling support, including development of a levelised cost of hydrogen tool to inform investment decisions.
Deliverables included feasibility and FEED reports, engineering design packages, cost estimates, and commercial modelling outputs.