Protos CCS

England

Project Factsheet

Fichtner provided comprehensive support in developing and procuring the Protos carbon capture and storage (CCS) scheme, the first major carbon capture scheme in the waste sector to achieve its Environmental Permit. We delivered both Technical Advisor (TA) and Owner's Engineer (OE) roles throughout the development stage, guiding the project from initial concept through procurement and regulatory approval. During early development, we assessed CCS technology suitability for integration with energy recovery facility (ERF) plants, then provided full technical and commercial support through bidding to the Department of Energy Security and Net Zero (DESNZ) for Track 1 of the Waste Industrial Carbon Capture (WICC) scheme. We completed the conceptual design and pre-FEED study that formed the basis for initial DESNZ bids. 

Our role expanded to include full procurement support, developing all contract documentation through market engagement, FEED, and EPC contracting stages based on IChemE forms, and we led development and agreement of all technical interface aspects with HyNet cluster counterparties, including the T&S Co.

We delivered comprehensive environmental engineering support, including Environmental Permit application development and submission with air quality assessment, and provided crucial planning application support, which has now been awarded. Additionally, we served as Lender's Technical Advisor (LTA), completing technical and commercial due diligence for project equity and debt providers. 

The project marks a pivotal advancement in waste sector decarbonisation. Once operational, the facility will enable permanent storage of approximately 350,000 tonnes of CO₂ emissions annually, representing a significant step toward the UK's net zero targets and a potential cornerstone of UK carbon capture initiatives, paving the way for future sustainable waste management developments.

CO₂ captured and stored annually
Key Facts

Engineering and advisory for a CCS project

  • Technical Advisor (TA)
  • Owner's Engineer (OE)
  • Initial CCS technology assessment
  • Technical and commercial support for DESNZ bidding (Track 1 WICC scheme)
  • Conceptual design and pre-FEED study
  • Procurement support and contract documentation development
  • Market engagement, FEED, and EPC contracting support (IChemE forms)
  • Interface development with HyNet cluster counterparties and T&S Co
  • Environmental engineering support
  • 350,000 tonnes of CO₂ captured and stored annually
  • First major carbon capture scheme in the waste sector to achieve Environmental Permit
  • Planning application awarded
  • Supported under Track 1 of the WICC scheme (DESNZ)