The proposed plant for the Hull project will be designed to treat approximately 214,000 tonnes per annum of refused derived fuel (RDF) and export about 24 MWe of electricity to the grid. The proposed technical solution is based on Outotec’s bubling fluidised bed staged gasification process, and consists of fuel reception, handling and storage, a fluidised bed gasification/combustion system, steam boiler, steam turbine/generator, air cooled condenser, flue gas treatment plant, and stack.

Acting as LTA, Owner’s Engineer and engineering consultant, our services included;

  • Technical due diligence;
  • Specification development;
  • Assessment of tenders;
  • Support for negotiations with shortlisted contractors;
  • Owners Engineer;
  • Full time site attendance;
  • CDM Advisory.

The Energy Works Hull Facility is the first waste project to be funded under the Government’s ‘Contract for Difference’ scheme, which have been put in place to stimulate investment in green energy developments to achieve targets for carbon reduction.

  • ISO 9001: Quality Management Systems
  • ISO 14001: Environmental Management
  • BS OHSAS 18001: Health and Safety Management
  • IChemE & IMechE Accredited Chartered Engineers
  • best copany
  • Gooad Recruitment
  • Investors in people
  • ISOQAR registered
  • Ichemf Acf
  • Institution of Mechanical Engineers